-
The Challenge for XRAIL XRAIL was successfully chosen by Siemens Mobility to undertaking the Corrective and Preventative maintenance for the Signalling...
-
The Challenge for XRAIL XRAIL were successfully appointed by Network Rail (NR) as technical experts for the East Coast Main line...
-
XRAIL was successfully chosen by Siemens Mobility to undertaking the Corrective and Preventative maintenance for the Signalling System and the...
-
XRAIL has a number of engineers who have considerable experience of the London Underground Infrastructure particularly associated within the Design...
-
The Riyadh Metro is a rapid transit system under construction in the city of Riyadh, the capital of Saudi Arabia....
-
The Dubai Metro is the world’s longest automated, driverless metro network. Its Red Line became operational on September 9, 2009; today...
-
London’s Waterloo station is one of the busiest railway stations in the UK, which provides more than half a million...
-
XRAIL’s scope of its bid, under the terms of the Colas Rail commission, required to : Axle Counters (AZLM) and HVI...
-
Since 2017 XRAIL has been working for a number of clients; Vital Projects, AMCO Giffen and QTS, on the CP5...
-
XRAIL was required to plan, manage and deliver the Signalling Installation for the associated bridge renewal at Bonhill Road, Dumbarton,...
-
XRAIL’s scope of its bid, under the terms of the Colas Rail commission, required to provide SMTH, Installation and Testing...
-
Following from the successful delivery of the signalling changes for the King’s Cross (H&C) End State Layout in December 2014,...
-
The Dubai Metro is the world’s longest automated, driverless metro network. Its Red Line became operational on September 9, 2009;...
-
XRAIL were asked to manage and provide a design package for the first of type In-Bearer Clamplock Points in the...
-
XRAIL recently played a key role in the design work required to deliver the new signalling changes for the End...
-
XRAIL has a number of engineers which are well versed with the application of the Thales TBTC System which was...
Our Work
XRAIL Group - Engineering TogetherCentral Line – Code Ripple Project
|
Home » Published: 6th February 2015 This Case Study was Written by: Munir Patel - XRAIL Group |
London Underground | March 2012 – Aug 2012 |
London Underground |
March 2012 – Aug 2012 |
XRAIL were asked to manage and provide a design package to resolve a “Code Ripple” occurrence at North Acton (Central Line). Code ripple can result from the operational characteristics of the Jointless Track Circuit (JTC) receivers used on the Central Line ATP System where two successive code changes occur in consecutive samples with insufficient sample time remaining in the sample period to register the change.
As a result of a review of data files provided from the asset performance during code ripple a cause and solution was identified to mitigate the effects of code ripple. The solution required the installation of six slow to pick relays on the code selection relays that cause the effect.
XRAIL has a number of engineers that have acquired extensive asset and systems knowledge of the Central Line signalling system obtained through involvement in the Central Line Re-signalling Project and subsequent designs to support such work packages as the Track Partnership Central Line Point Replacement Project that consisted of circuit and Westrace ladder logic alterations. Each engineer also held the appropriate IRSE Licenses to the specific role required.
The design was produced in line with the existing Westrace Interface Circuit Specification and relevant engineering standards. Key deliverables;
- An assessment of a suggested solution previous identified in a study produced on the code ripple occurrence at North Acton and determine its acceptability.
- Production of a pre-design correlation pack to correlate 5 relay equipment racks and review of the resultant correlation returns.
- Provision of design reviews with relevant parties to assess whether the selected design solution would require a single design or staged design to facilitate Engineering Hours commissioning.
- Provision of a material ordering schedule.
- Production of staged designs that allowed the circuit alterations to be incorporated through a plate racking system allowing ease of testing and commissioning.
- Provision of a compliance submission and design check certificate.
- Provision of a commissioning correlation pack and review of the resultant correlation returns.
The following roles were undertaken by the engineers to provide the project delivery;
- Design Delivery Engineer
- Design Preparer
- Design Checker
- Design CAT ‘S’ Approver
- CAD Engineer
The Engineers are all recognised as Approvers under the LU Asset Competency system.
The project introduced a number of technical and programme problems. These are the challenges that were faced and resolved:
- The works to be delivered required the engineers to assess the effects of the proposed design solution against the complex Central Line transmission based ATP code system to assure that the change would not adversely affect the ATP code system. Several design reviews were conducted to ensure the option selected would resolve the code ripple effect without the impact on existing assets and would be cost efficient.
- As a result of design reviews and discussions with the Tester in Charge and Asset Engineer the resultant design was required to be produced as a staged designs that allowed the circuit alterations to be incorporated through a plate racking system allowing ease of testing and commissioning. The design was produced in line with the existing Westrace Interface Circuit Specification and relevant engineering standards.
Over the course of six months the engineers overcame some of the challenges above and many product related issues.
The outcome was successful as the engineers were instrumental in the delivery and assurance of the design produced for London Underground was accepted.
In summary, through a detailed design review, the complexities that caused the code ripple occurrence specific to North Acton and the subsequent application design allowed the signalling modification to the ATP code selection circuits to be commissioned in engineering hours. This met the requirements of both the Tester in Charge and the Signalling Asset Engineer, with the commissioning now planned in Sept 2012.