End State Layout – Earl’s Court (District)

Munir Patel - XRAIL Group

Home » End State Layout – Earl’s Court (District)

Published: 8th April 2019

This Case Study was Written by: Munir Patel - XRAIL Group

   ,


  London Underground   January - December 2017
  London Underground
  January - December 2017

Following from the successful delivery of the signalling changes for the King’s Cross (H&C) End State Layout in December 2014, XRAIL were contracted out to provide similar support to the Earl’s Court Ends State Layout Project.

XRAIL engineers played a key role in the signal engineering work required to deliver the signalling project requirements for the upgraded layout east of Earl’s Court station (District Line).

Principles Engineers from XRAIL, under a consultancy agreement with LU CPD, provided the majority of the design and systems engineering capability required to produce the key signalling deliverables for the project.

The work consisted of providing all the signalling modifications required to enable the installation and commissioning of new flat-bottom rail junctions east of the station. This included the replacement of 7 points with modern Surelock machines to current standards. The aim was to bring forward the benefits of higher turnout speeds in the area and realise important operational benefits to the SSR network in advance of the 4LM programme.

In addition to the above benefits, the project was to implement:

  • Track upgrades under a BTR programme
  • Traction power upgrades including new sectionalisation arrangements
  • SPAD mitigations for signals on the Operator’s list
  • New points kiosks designed and constructed with the interface circuitry required for the operation and detection of the points to be readily migrated to the 4LM signalling system.

The project was multi-discipline and complex by nature; over its 12-month duration, our engineers were actively involved in managing:

  • the signalling interfaces with the Systems, Track, P-Way, Power and Civil disciplines as well as supporting the Installation, test & Commission Engineers
  • The point interface requirements from the 4LM project
  • The interfaces with the stakeholders including the Sponsor, the Maintainer and the Operator

More XRAIL Case Studies...

Overview of deliverables:

  • Signalling design deliverable

These included: Desktop reviews; overlap calculations; scheme plan production; operational concepts; bookwiring circuit designs; scale plan and traffic controller diagrams; cable running charts and asset condition reports for the Earl’s Court interlocking area.

  • Systems Engineering deliverables

These included: Project requirements elicitation and capture; CDS production; coordinated system modelling and system performance integration; requesting the train performance modelling required; providing support to the project in terms of requirements V&V; coordination of the interface between Power, Civil and Track disciplines as well as the 4LM project through inter-discipline design reviews and acceptance of the proposed schemes from those discipline engineers; leading the buildability reviews with the Installer; updating Hazard logs and participating in Hazid reviews; producing designer’s risk assessments and other data required for the H&S files held by the project; providing design assurance to the project in accordance with S1538 and the Category ‘S’ level of design approval; providing fully accepted designs with the required design check certificates; gaining design compliance from the Asset Engineer’s accredited independent reviewer.

XRAIL personnel deployed and their competencies:

Three IRSE licensed Principles Engineers from XRAIL were assigned to the project with a contract to provide the deliverables listed above. These engineers were carefully selected from their previous experience on LU conventional signalling system design based on technical competence matrix.

Project cost savings through judicious use of resources:

By agreeing to position suitably licensed and experienced principle engineers within the Client’s organisation and using the Client’s planner, and additional designers, XRAIL was able to help the Client realise significant reductions in the project’s design costs – typically up to 18% on the overall signalling design. This cost saving stems from having a team imbedded within the Client’s organisation and thus reducing the interface management burden with the project team and other engineering disciplines. The activities included:

  • inter-discipline reviews
  • design and buildability reviews
  • review and acceptance of track and power scheme designs
  • review of 4LM’s interface requirements for points kiosks
  • validation of source information and records for the designs
  • implementation of the Client’s standards and procedures
  • management of stakeholders such as the operational representatives, sighting party committees and maintainers
  • management of the interface with the Client’s installation, test and commissioning contractor
  • management of contract variations
  • management of concessions to standards
  • management of asset record updates and the MAID process for completion and handover

The XRAIL engineers lead in many aspects of the design process ranging from requirement capture, CDS production, review of other engineering discipline CDS and participation in IDRs, regular programme updates, progress reports, contractor communication, technical queries, requests for information and early warning notices.

Meeting programme deadlines:

Through a proactive participation in the project planning and accurate progress reporting, the XRAIL engineers supported the project planner.

The design was produced within the unusually short timescale agreed by adopting an innovative staging approach to support the installation contractor’s work programme. This was achieved by issuing the design in packages under ‘consent to install’ and gradually building up to the final issue for commissioning during the Christmas closure. With this approach we were able to help the project beat its programme deadline as the installation and pretesting was completed in early December in readiness for the Christmas closure. This represents approximately a 3-week early completion ahead of schedule over a 26-week programme (i.e. 11% reduction).

Value added initiatives:

  1. The engineers from XRAIL provided mentoring and on-the-job training of junior members of the Client’s design team thus helping them gain their IRSE license within a shorter timeframe.
  2. The engineers from XRAIL were able to argue and gain support from the signalling asset maintainer and the track engineer for replacing unnecessary twin track circuit blockjoints where possible with single joints. This was done very cost-effectively as part of the BTR programme and represented a significant savings on the number of blockjoints in the area and hence, reduced failure points and maintenance costs.

More XRAIL Case Studies...