-
The Challenge for XRAIL XRAIL was successfully chosen by Siemens Mobility to undertaking the Corrective and Preventative maintenance for the Signalling...
-
The Challenge for XRAIL XRAIL were successfully appointed by Network Rail (NR) as technical experts for the East Coast Main line...
-
XRAIL was successfully chosen by Siemens Mobility to undertaking the Corrective and Preventative maintenance for the Signalling System and the...
-
XRAIL has a number of engineers who have considerable experience of the London Underground Infrastructure particularly associated within the Design...
-
The Riyadh Metro is a rapid transit system under construction in the city of Riyadh, the capital of Saudi Arabia....
-
The Dubai Metro is the world’s longest automated, driverless metro network. Its Red Line became operational on September 9, 2009; today...
-
XRAIL’s scope of its bid, under the terms of the Colas Rail commission, required to : Axle Counters (AZLM) and HVI...
-
Since 2017 XRAIL has been working for a number of clients; Vital Projects, AMCO Giffen and QTS, on the CP5...
-
XRAIL was required to plan, manage and deliver the Signalling Installation for the associated bridge renewal at Bonhill Road, Dumbarton,...
-
XRAIL’s scope of its bid, under the terms of the Colas Rail commission, required to provide SMTH, Installation and Testing...
-
Following from the successful delivery of the signalling changes for the King’s Cross (H&C) End State Layout in December 2014,...
-
The Dubai Metro is the world’s longest automated, driverless metro network. Its Red Line became operational on September 9, 2009;...
-
XRAIL were asked to manage and provide a design package for the first of type In-Bearer Clamplock Points in the...
-
XRAIL recently played a key role in the design work required to deliver the new signalling changes for the End...
-
XRAIL has a number of engineers which are well versed with the application of the Thales TBTC System which was...
-
XRAIL were asked to manage and provide a design package to resolve a “Code Ripple” occurrence at North Acton (Central...
Our Work
XRAIL Group - Engineering TogetherWaterloo Station Remodelling
|
Home » Published: 18th March 2022 This Case Study was Written by: Munir Patel - XRAIL Group |
Colas Rail | 2015 - 2017 |
Colas Rail |
2015 - 2017 |
London’s Waterloo station is one of the busiest railway stations in the UK, which provides more than half a million passenger journeys a day and 230 million a year.
An £800m investment plan for the station upgrades was unveiled in March 2016. The project was managed by Network Rail and sponsored by the UK’s Department for Transport, South West Trains, Transport for London, and Wessex Capacity Alliance. The site preparation works on the station upgrade began in October 2015 and construction works began in December 2015.
The commission to undertake work at Waterloo Station was based on XRAIL’s engineers’ proven capability and knowledge of key roles working on TfL infrastructure namely, Jubilee & Northern Line Upgrade Project and Network Rail.
XRAIL Group Scope and deliverables:
- Programme Planning – P6 plan Gannt Chart,
- Resourcing Roster, Time sheets & Mac Rail reports
- Installation Method Statements
- Daily Site reports, Record of Site Safety briefings &
- Close call reporting
- Monthly environmental KPI reports
- Installation and Test logs
- Installation Test Certificates
- Installation release notice
More XRAIL Case Studies...
Equipment Installation included:
- EBI 4000 Track circuits
- DTU’s
- Station Area Control Units
- End Tuning Unit -‘Z’ bonds
- HW point machines
- AWS
- TPWS
- Buffer Stop Mini Loops
- Trackside Disconnection Boxes
Testing:
- All cabling was tested after installation and IRN and relevant cable certificates were issued to functional test team
Challenge
A significant project challenge was the limited amount of time available for the work and the capacity of installation and testing staff to safely undertake the volume of work within available access hours.
Solution
XRAIL Limited having previous experience of working to compressed delivery schedules, undertook an assessment of the proposed installation and testing strategy. and determined that a cost and time opportunity existed by changing the proposed installation from 100% on-site fabrication to a combination of off-site batch production and reduced on-site working.
Three areas of potential opportunity were identified:
- Pre- configuration and assembly of diss-connection boxes – Measurements were taken of a range of cables that were identified as suitably low risk and a process of off-line batch assembly was adopted. Cables were accurately measured, cut to length and one end pre-terminated into the pre-configured dis-connection boxes. Cables were then coiled and secured for transit to site to be used during the next on-site installation period.
- Split team to undertake installation/removals – A revised work breakdown schedule (WBS) was created that re-sequenced work such that installation teams were split into two dedicated sections. The first, would lead in tagging and disconnection, followed by the second team dedicated to asset removal and installation of new pre-fabricated disconnection boxes.
- Use of engineers with previous experience – To facilitate the accelerated installation to reduce timescales and de-risk the project overrun XRAIL utilised technically experiences staff to undertakethe works.
The Benefits
Engaging with an experienced and competent organisation significantly reduced the base risks associated with the technical project delivery, a significant factor when considering the safety critical nature of signalling system changes and modifications.
XRAIL Group staff added additional value beyond the delivery of the technical scope by de-compressing the delivery schedule through the revised WBS but also de-risked the project from installation delay and service affecting failures by preserving “wheels free access” and testing time. XRAIL staff utilised included experienced installers and wiremen able to undertake these tasks quickly and efficiently
Reduced on site working of 12% and optimisation of the client programme WBS resulted in delivery efficiency through a more focussed and repetitive installation from each dedicated section.